Planning and scheduling are not the same
Planning means defining what will be done and with what: scope, steps, spare parts, tools, labour hours and safety conditions. Scheduling means deciding when and by whom it is done, according to the priority of the job and the availability of the equipment and the people. When the two tasks are mixed, the urgency of the day ends up displacing preparation.
The workflow
- Identification: operator requests, inspection rounds and condition monitoring results.
- Prioritisation according to equipment criticality and the consequence of failure.
- Planning the work order: scope, procedure, spare parts, labour hours and permits.
- Weekly schedule agreed with operations.
- Execution and recording of what was actually done.
- Closing the order and feeding back into the plan and the equipment history.
Indicators to track the process
A worked example
A maintenance team has 1,200 labour hours of pending work and 400 labour hours available per week. Last week 50 orders were scheduled and 42 were completed.
- Backlog
- 1,200 ÷ 400 = 3 weeks
- Schedule compliance
- 42 ÷ 50 = 84%
A backlog of a few weeks indicates a manageable workload. If it grows steadily, resources are short or the preventive plan is oversized. If it is close to zero, jobs are probably not being identified.
What keeps the plan healthy
- An up-to-date criticality analysis, so that priority does not depend on who complains loudest.
- Preventive tasks justified by a failure mode, reviewed with RCM or FMEA.
- Reliable failure history, recorded when each order is closed.
- A weekly scheduling meeting between maintenance and operations.